Click on any of the thumbnail pictures to see a larger version.
| Barbados National Terminal Project |
| Project: fabrication of three Steel Mooring Buoys for the Barbados National Terminal Company Ltd. offshore berth, Oistins Bay, Barbados. Hystar Marine's work included supply of critical components including two degrees of freedom Quick Release Hooks and Connection Collars, rubber buoy fenders, anodes, anchor chain and miscellaneous hardware. Buoys were fabricated in Barbados under the supervision of Hystar Marine Inc. on behalf of SBS Projects Inc and Marenco Ltd. of Barbados as subcontractors to the Commonwealth Construction Canada Ltd. |
 |
 |
 |
 |
| Worker in Barbados grinding on the Inside of the buoy |
One of three 11'-6" diameter by 8' tall buoys |
Detail of Quick Release Connection Collar |
Finished Buoys complete with two degrees of freedom Quick Release Hooks and Connection Collars |
| Concrete Anchor Blocks for Mooring System: Cascadia Forest Products |
| Project: To manuafacture and load 2 Anchor Blocks onto a barge for installation at the Queen Charlotte Islands Division of Cascadia Forest Products. The single point anchoring system is used for tying up log barges. |
 |
 |
 |
 |
| 60 ton block ready to load at Richmond BC dock facility |
Placing of the 60 and 30 ton blocks on the stern of a barge |
60 ton anchor block coming to rest on barge |
Both blocks on the barge |
| Sechelt Waterfront Ship Loading Facility |
| This installation of four custom buoys was designed and installed for Construction Aggregate’s new Deep Sea Loading Facility in Sechelt, British Columbia, Canada. The sequence of Photos shows stages of the project. These buoys are ballasted with 22300 lbs. of concrete each. They are used to tie up 70,000 ton self-unloading gravel freighters. Originally these steel tanks were used as bentonite tanks on a supply ship. |
 |
 |
 |
 |
| Steel Tanks arriving to the Hystar Marine Facility |
Removing external structure to streamline buoy shape |
Restoration process |
Finish coat of marine epoxy paint |
 |
 |
 |
 |
| Crane lifting units for transport to the Sechelt Harbour |
Buoys securely anchor large ships while being loaded with gravel from the Sunshine Coast |
|
Closeup view |
| Refurbished / Modified Buoy : Roberts Bank Coal Port Facility, Delta BC |
| Project: to Modify and Refurbish a 17 foot diameter by 7 foot high Steel Buoy that will continue to be used at the Roberts Bank Coal Port Facility , Delta, BC by Westshore Terminals |
 |
 |
 |
 |
| The "Before" Picture |
Sandblasted and Primed |
Spraying marine paint : color coat |
The "After Picture" |
|
|
 |
A similar restoration project:
Refurbished and Modified Buoy, complete with Quick Release Hooks and Hystar designed Connection Collar |
| Residential Foreshore Projects |
| This custom Stair Project, utilizing concrete and clear Red Cedar, allowed easy access to the sea from the residence on the rock bluff. |
 |
 |
 |
|
|
|
|
|